Ambler Boiler House

Maple Street • Ambler, PA
resize may 1 car
Additional Ambler Boiler House Photos
After sitting empty since the mid 1970’s the first phase of the Ambler Boiler House is completed. Domus, Inc has been involved in the project since 2001 when it was contracted by Summit Realty to provide pre-construction services. The Boiler House will be the center of a Transit Oriented Development (TOD) that contains 42,273 square feet of office space and has received LEED Platinum certification. The work consisted of restoration of the masonry walls and steel, new windows and roof and the installation of a geothermal system for heating and cooling

Project Details

Primary Funding Source

Government and Private Funds

Size

42,000 sq.ft

Completion Date

June 2012

Contract Amount

$8,254,000

Owner/Client Information

Ambler Station Associates

Contact: John J. Zaharchuk

Architect Information

Heckendorn Shiles Architects

>